Timeline

October
10/19-Loan Pre-Approval
10/20: Put a down deposit on our preferred lot
10/21: Signed the purchase agreement
11/26: Loan Appointment/Guardian Appointment

November
11/4: Change Order Appointment
11/11: Flooring Appointment
11/11: Pre-Construction Meeting
11/18: Loan Approval
11/24: Broke Ground

December
12/11: Helical Piers were installed
12/14: Footers
12/16: Foundation
12/29: Locked in rate with NVR
12/31: Framing Started

January
1/6: Framing Completed
1/7: Plumbing and HVAC started
1/11: Wiring Appointment
1/14: Pre-Drywall Walkthrough
1/30: Trim started

February
2/4: Floors/granite installed and appliances delivered
2/12:Fixtures installed
2/26:Independent Inspection

March
3/1: Final Walkthrough/Closing




No comments:

Post a Comment